Resourceful Earth

Published: 23 January 2019

An update from the Resourceful Earth planning agent (about site off Charlton Road, near Keynsham):

Notice of minor works to be undertaken at the site known as Resourceful Earth Ltd, Charlton Field Lane, Queen Charlton, Bristol, BS31 2TN. (top of Charlton Road) over the next few weeks for a number of reasons including health and safety.

As the site is currently a dormant construction site, the site manager needs to ensure that the machinery on-site is protected as well as ensuring that the site is adequately sealed off from the public for health and safety reasons. The works will inherently involve contractors coming to site, deliveries and machinery operating, therefore I wanted to update you beforehand and to confirm that there is no new construction taking place on the site.

Work period January/February

Task: Installing replacement and additional construction fencing to ensure the construction site is adequately sealed off for health and safety reasons.
Expected start date: January/ February 2020.
Expected Duration: 5 days.
Deliveries to site: Yes to deliver the fencing and forklift.
Machinery required on site: Forklift.
Personnel undertaking task: 2.

Task: Conduct engine preservation for the 4 engines to safeguard their integrity whilst not in use.
Expected start date: February 2020.
Expected Duration: 2 days.
Deliveries to site: No, all equipment will be brought in to site by the engineer.
Machinery required on site: No.
Personnel undertaking task: 1.

Task: Removal of the digester tank roofs to preserve the roofs, reduce electrical consumption for the site and remove the need to maintain them at height whilst not in use.
Expected start date: February 2020.
Expected Duration: 3 days.
Deliveries to site: Yes to deliver the machinery.
Machinery required on site: Yes, a crane, a telehandler and a cherry picker.
Personnel undertaking the task: 5.